Skip to content
VUBuddy

MTH601 Practice Questions Lectures 4-20 Set 2

Operations Research PDF 434 KBUpdated 23 Oct 2026
Quiz MTH601 Practice Questions Lectures 4-20 Set 2 PDF 434 KB
vubuddy.com
Type
Quiz
Course
MTH601 Operations Research
Size
PDF 434 KB
Updated
23 Oct 2026
Free download 0 of 3 used today
Download free · 434 KB

You get 3 free files a day on the website. Add the Chrome extension for 30 a day.

Unlimited downloads in the Android app Get it free on Google Play

Preview text

Text from pages 4, 5, 6 of 39. Download the file for all 39 pages.

Q1. Which of the following in the highway system has the same analogy as that of the flow branches and nodes of the network flow diagram.

  1. Roads
  2. Intersection
  3. Vehicles

Solution

a. Roads have the same as analogy as that of branches in network flow diagram. b. Intersections have the same as analogy as that of nodes in network flow diagram. c. Vehicles have the same as analogy as that of flow in network flow diagram.

Q2. Define the following

  1. Dummy activity and its use
  2. Looping error in network
  3. Dangling error in network.

Solution

a. Dummy activity and its use:

In large networks the easiest way to represent some precedence relationship is by introducing the dummy activity. It does not consume any time or any kind of resource. It makes the calculation we have to do easier to follow and maintain the correct sequence of activities. Dummy activity is introduced in a network under the following situations.

  •  Created to make activities with common starting and finishing events distinguishable.

To identify and maintain the proper precedence relationship between activities those are not connected by events.

  1. Looping Error in Network:

If some activities in a network form a loop (or cycle), then such error in network is called looping error as shown in the figure below: In the above network B, C and D form a loop (cycle).Thus the network cannot proceed. Such situations can be avoided by checking the precedence relationship of the activities.

c. Dangling Error in Network:

If in a network some activity other than the final activity do not have successor activity then it is called a dangling error in a network. Such end events other than the end events of the project are called dangling events. Thus in a network all events except the first and last of the whole project must have at least one entering and one leaving activity.

In the network shown above the activity D leads to dangling .To avoid this dangling we introduce a dummy activity between the end event of this activity and the end event of the project.

Q4. Draw a network diagram for the set of activities below

Activity

A B A C A D B E C F D,E G F D

A B C

E

C E

G

D B F

A

Solution

Q5. Define the following terms

  1. Earliest Start Time
  2. Earliest Finish Time
  3. Latest Start Time
  4. Latest Finish Time

Solution

a. Earliest Start Time(EST):

It is the earliest possible time by which an activity can start. It is calculated from the earliest start time of the tail event.

b. Latest Finish Time (LFT):

It is the latest possible time when an activity should end. It is calculated from the latest finish time of the head event .For its calculation we require the total project time.

c. Earliest Finish Time (EFT):

EFT=EST+ Duration of the activity.

d. Latest Start Time (LST):

LST=LFT-Duration of activity.

Q6. Construct a table for the network diagram which shows the relationship between activities and their predecessors.

F(4) B(6) D(7)

C(10) E(2) G(5) A(1)

All MTH601 files →
MTH601 Operations Research All MTH601 handouts, past papers, quizzes and MCQs in one place. Open course page

Get more out of VUBuddy, for free

Android app Free on Google Play
  • Unlimited downloads
  • The explanation behind every MCQ answer
  • Study offline on slow data
Get the Android app
Chrome extension Free on the Chrome Web Store
  • 30 downloads a day instead of 3
  • Sign in and buy Pro Semester here
Add to Chrome

One Pro Semester membership works in both the extension and the app.