Q1. Which of the following in the highway system has the same analogy as that of the flow branches and nodes of the network flow diagram.
Solution
a. Roads have the same as analogy as that of branches in network flow diagram. b. Intersections have the same as analogy as that of nodes in network flow diagram. c. Vehicles have the same as analogy as that of flow in network flow diagram.
Q2. Define the following
Solution
a. Dummy activity and its use:
In large networks the easiest way to represent some precedence relationship is by introducing the dummy activity. It does not consume any time or any kind of resource. It makes the calculation we have to do easier to follow and maintain the correct sequence of activities. Dummy activity is introduced in a network under the following situations.
- Created to make activities with common starting and finishing events distinguishable.
To identify and maintain the proper precedence relationship between activities those are not connected by events.
If some activities in a network form a loop (or cycle), then such error in network is called looping error as shown in the figure below: In the above network B, C and D form a loop (cycle).Thus the network cannot proceed. Such situations can be avoided by checking the precedence relationship of the activities.
c. Dangling Error in Network:
If in a network some activity other than the final activity do not have successor activity then it is called a dangling error in a network. Such end events other than the end events of the project are called dangling events. Thus in a network all events except the first and last of the whole project must have at least one entering and one leaving activity.
In the network shown above the activity D leads to dangling .To avoid this dangling we introduce a dummy activity between the end event of this activity and the end event of the project.
Q4. Draw a network diagram for the set of activities below
Activity
A B A C A D B E C F D,E G F D
A B C
E
C E
G
D B F
A
Solution
Q5. Define the following terms
Solution
a. Earliest Start Time(EST):
It is the earliest possible time by which an activity can start. It is calculated from the earliest start time of the tail event.
b. Latest Finish Time (LFT):
It is the latest possible time when an activity should end. It is calculated from the latest finish time of the head event .For its calculation we require the total project time.
c. Earliest Finish Time (EFT):
EFT=EST+ Duration of the activity.
d. Latest Start Time (LST):
LST=LFT-Duration of activity.
Q6. Construct a table for the network diagram which shows the relationship between activities and their predecessors.
F(4) B(6) D(7)
C(10) E(2) G(5) A(1)
Related MTH601 files
All MTH601 files →- MTH601 Highlighted Handouts by One Step to Success Highlighted PDF 8.1 MB
- MTH601 Midterm Past Papers by Rana Abubakar Khan Midterm PDF 498 KB
- MTH601 Quiz Saima Kanwal by One Step to Success Quiz PDF 435 KB
- MTH601 Quiz 2 Quiz PDF 2 MB
- MTH601 Practice Questions Lectures 5-6 Quiz PDF 35 KB
- MTH601 Subjective Subjective PDF 7 MB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.