Which of the following in the highway system has the same analogy as that of the flow branches
and nodes of the network flow diagram
Roads
Intersection
Vehicles
Define the following
a) Dummy activity and its use
b )Looping error in network
c) Dangling error in network
What is PERT? How it is different from CPM?
Draw a network diagram for the set of activities below
A
B A
C A
D B
E C
F D,E
G F
Define the following terms
- Earliest Start Time
- Earliest Finish Time
- Latest Start Time
- Latest Finish Time
Construct a table for the network diagram which shows the relationship between activities and their
predecessors.
Calculate EST and EFT for each job of the following data.
P(1-2)
Q(1-3)
R(2-3) P
S(2-4) P
T(3-4) R,Q
If project completion date is 38 days for the following data then find the LST and LFT for the
following data.
P(1-2)
Q(1-3)
R(2-3) P
S(2-4) P
T(3-4) R,Q H
D A C E G
F
B
J I
Related MTH601 files
All MTH601 files →- MTH601 Handouts Lectures 1-45 Handout PDF 1.1 MB
- MTH601 Final Term Past Paper Spring 2006 Final term PDF 143 KB
- MTH601 Quiz 2 Lectures 12-18 Quiz PDF 4.2 MB
- MTH601 Operation Research Quiz by VUBuddy Quiz PDF 985 KB
- MTH601 Grand Quiz Set 3 Quiz PDF 1.4 MB
- MTH601 Practice Questions Lectures 4-20 Set 2 Quiz PDF 434 KB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.