Q1. Which of the following determines the scope and risks and identify the objectives of testing?
Correct answer: Planning and control
Q2. Test objectives should measure the ___________ of a test case.
Correct answer: outcome
Q3. In fault seeding, confidence C is calculated by ___________.
Correct answer: C = S/(S + N + 1)
Q4. Test engineers do regression testing at the ____________ level.
Correct answer: system
Q5. Which of the following color is used to show unsuccessful test cases in Microsoft Test Manager (MTM)?
Correct answer: Red
Q6. Bug is the same name of _______.
Correct answer: Defect
Q7. Test plan and _____________ are the first and last steps of Test Data Management respectively.
Correct answer: test run
Q8. Which of the following is the size of team in Fagan inspections for verification?
Correct answer: 4
Q9. What is the correct sequence from informal to formal in verification methods?
Correct answer: Informal, Walkthrough, Peer review, Inspection
Q10. Which of the following is to measure the outcome of the test case?
Correct answer: Test outcome
Related CS608 files
All CS608 files →Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.