CS615 Final Term MCQs with References by Faisal

Software Project Management PDF 793 KBUpdated 23 Oct 2026
Final term past paper CS615 Final Term MCQs with References by Faisal PDF 793 KB
vubuddy.com
Type
Final term past paper
Course
CS615 Software Project Management
Size
PDF 793 KB
Updated
23 Oct 2026
Free download 0 of 3 used today
Download free · 793 KB

You get 3 free files a day on the website. Add the Chrome extension for 30 a day.

Unlimited downloads in the Android app Get it free on Google Play

Preview text

Text from pages 1, 2, 3 of 50. Download the file for all 50 pages.

 MUHAMMAD FAISAL  · MIT 4th Semester · Al-Barq Campus (VGJW01) Gujranwala · Reference MCQ’s For Final TERM EXAMS · CS615- Software Project Management

Q1. (1 marks)

  1. None of given
  2. Program
  3. Task (page 275)
  4. Project

Correct answer: Task (page 275)

Q2. (1 marks)

  1. Function point sizing (page227)
  2. Standard component sizing
  3. Change sizing
  4. All of given

Correct answer: Function point sizing (page227)

Q3. (1 marks)

  1. Program WBS
  2. Contract WBS (page249)
  3. Contract Program WBS
  4. None of given

Correct answer: Contract WBS (page249)

Q4. Which of the following Technique use network schedules to trace the completion of predetermined activities? (1 marks)

  1. Gantt Charts
  2. PERT
  3. CPM
  4. PERT and CPM (page 296)

Correct answer: PERT and CPM (page 296)

Q5. The decomposition of a software project is one of the first tasks of ________. (1 marks)

  1. Software Engineer
  2. Software project manager (page 264)
  3. Software Analyst
  4. Software tester

Correct answer: Software project manager (page 264)

Q6. (1 marks)

  1. Project life-cycle-based
  2. Scheduled
  3. None of given
  4. Deliverable-based (page 277)

Correct answer: Deliverable-based (page 277)

Q7. Risk analysis and management are a series of steps that help a software team to understand and manage________. (1 marks)

  1. Uncertainty (page 305)
  2. Crises
  3. None of given
  4. Problem

Correct answer: Uncertainty (page 305)

Q8. Lessons learned are important to document because on organization can use them to improve future projects and the Project Management process. Therefore, in project closing procedures, it is helpful to review the: (1 marks)

  1. Checklists for risk identification
  2. WBS
  3. Original contract
  4. All of given

Q9. Predecessor activities need to________ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. (1 marks)

  1. Both start and end
  2. End (page 297)
  3. Start
  4. None of given

Correct answer: End (page 297)

Q10. To________ risks from occurring, the project team prepares the risk plan before the commencement of the project. (1 marks)

  1. Avoid (page 312)
  2. Deal
  3. None of given
  4. Manage

Correct answer: Avoid (page 312)

Q11. (1 marks)

  1. None of given
  2. Program
  3. Task (page 275)
  4. Project

Correct answer: Task (page 275)

Q12. A________ is defined as "the work breakdown that covers the acquisition of a specific defense material item and is related to contractual effort." (1 marks)

  1. Program WBS (page 250)
  2. Contract WBS
  3. Contract Program WBS
  4. None of given

Correct answer: Program WBS (page 250)

Q13. Scheduling for software engineering projects can be viewed from________ rather different perspectives. (1 marks)

  1. One
  2. Two (page 284)
  3. Three
  4. Four

Correct answer: Two (page 284)

All CS615 files →
CS615 Software Project Management All CS615 handouts, past papers, quizzes and MCQs in one place. Open course page

Get more out of VUBuddy, for free

Android app Free on Google Play
  • Unlimited downloads
  • The explanation behind every MCQ answer
  • Study offline on slow data
Get the Android app
Chrome extension Free on the Chrome Web Store
  • 30 downloads a day instead of 3
  • Sign in and buy Pro Semester here
Add to Chrome

One Pro Semester membership works in both the extension and the app.