Which of the following reason is more important to be handled to prevent project delay A. Human Defficulties B. Technical Defficulties
C. Unrealistic initial deadline
D. Known risks
Estimating the effort in the basic COCOMO technique involves following three steps except:
A. Calculating the effort adjustment factor
B. Determining the effort constants based on the type of the project C. Estimating the total delivered lines of code D. Substituting values for lines of code and effort constant in a formula
It is the ______________responsibility to select the structure best suited for the project. A. Planner
B. Project Manager's Page 48
C. Process Manager's D. Product Manager's
COCOMO stands for _____________________. A. Cost Consecutive Model
B. Constructive Cost Model
C. Consecutive Cost Model D. Cost Constructive Model
The Delphi technique is a _____________estimation technique.
A. Human-based Page 237
B. AI-based C. Computer-based D. Robotic-based management tasks except: A. Administration and services B. Planning C. Staffing
D. Acceptance
An industry standard rule of thumb is to make work packages that can be completed in timeframes of ________ weeks. A. Three
B. Two Page 287
C. One D. Four
In Work breakdown structure (WBS) subprojects are subdivided into smaller, more manageable work components (_________________) at the lowest level.
A. Work packages
B. Areas C. Project activities D. Sub-projects
All of the following are the High level WBS structure tasks in software development tasks except: A. Prototype implementation
B. Software integration
C. Prototype specification D. Prototype design
_________ define what kinds of competencies are required from what kinds of individuals or groups and in what time frames.
A. Staffing requirements Page 203
B. Constraints C. Project Interfaces D. Organizaion Planning
In planning process tasks, _____________ cannot be fixed and cannot be determined in the beginning. A. Vendor factor B. Cost factor
C. Scope factor
D. Owner factor
The answer of the _____________ question helps in defining a management and technical strategy for the project.
A. How will the job be done technically and managerially?
As project development progresses tasks in the WBS list should be
A. Removed B. Added
C. Added, Modified and Removed
D. Modified
The COCOMO technique has ______________levels of implementation. A. Two B. One
C. Three Page 233
D. Four
_____________ will assemble larger work packages that can be appropriately managed and controlled.
Related CS615 files
All CS615 files →Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.