Q1. Typically, a Program WBS consists of the upper ____________________ levels.
Correct answer: Four
Q2. All of the following are the High level WBS structure tasks in management tasks except:
Correct answer: Software enhancement
Q3. To aid planning, scheduling, and monitoring a project, you can use tool(s)________
Correct answer: All of the given
Q4. _____________ will assemble larger work packages that can be appropriately managed and controlled.
Correct answer: Larger projects
Q5. All of the following are the High level WBS structure tasks in Documentation tasks except:
Correct answer: Deliverable development documentation
Q6. A formal WBS may serve no useful purpose on a very small project, but it can become valuable if project size or complexity ________________.
Correct answer: Start to increase
Q7. All of the following are the High level WBS structure tasks in software development tasks except:
Correct answer: Prototype specification
Q8. In Work breakdown structure (WBS) a project may be divided into _______________.
Correct answer: Work packages
Q9. The COCOMO technique has ______________levels of implementation.
Correct answer: Three
Related CS615 files
All CS615 files →Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.