Q1. Vu-Topper RM (1 marks)
The first step in a problem-solving exercise in OR is the ________that exist in the system.
A. Construction of the model of problem
Q2. Vu-Topper RM (1 marks)
A requirement for the definition of the problem in OR is that ______must be clearly defined which helps to focus attention on what the problem is
A. Objective
B. Subjective
Q3. Vu-Topper RM (1 marks)
In a network flow diagram, time follows from_________
A. Left to right
B. Right to left
Q4. Vu-Topper RM (1 marks)
In a national highway system intersection of two or more roads has the same analogy as the ____in the network flow diagram.
A. Node
B. Point
Q5. Vu-Topper RM (1 marks)
In ______, activity time estimates are distributed according to beta distribution
A. PERT
B. Critical
Q6. Vu-Topper RM (1 marks)
In a transportation problem the objective function 'Z’ gives
A. Total Cost of transportation
B. Total time of transportation
Q7. Vu-Topper RM (1 marks)
In two phase method process, first phase the sum of artificial variables.
A. Minimize
B. Maximize
Q8. Vu-Topper RM (1 marks)
which of the following difficult may found while attempting an LP problem by M-method?
Correct answer: Computational error due to large value of m
Q9. Vu-Topper RM (1 marks)
Dual of a Dual is--------.
A. Primal
B. Dual
Q10. Vu-Topper RM (1 marks)
Shortcoming of Big M method is that the value of M could be _. A. Very small
B. Very large
Q11. Vu-Topper RM (1 marks)
In simple method to solve an LP problem gauss Jordan Elimination method demands that all the key column enters should be zero except. A. 1st row entry
B. Key row
Q12. Vu-Topper RM (1 marks)
Which of the following technique to solve the network flow diagrams is activity oriented?
Correct answer: Critical path method
Q13. Vu-Topper RM (1 marks)
Under which of the following condition a mathematical program would be non-linear?
Correct answer: If both objective function and constraints are non-linear
Q14. Vu-Topper RM (1 marks)
The amount of the inventory will always taken to be
A. Negative
B. Positive
Q15. Vu-Topper RM (1 marks)
Solution region of the constraints 2x+3y>12 or 6x+9y=36 Will be the half plane bisected by 2x+3y=12. A. Excluding
B. Including
Q16. Vu-Topper RM (1 marks)
Solution region of the constraints :2x+3y>12 and 2x+3y<12 will be the. Point (6,4) Straight line:2x+3y-12
A. Empty set
B. All first quadrant
Q17. Vu-Topper RM (1 marks)
Which of the following method follows iterative procedure to solve a linear programming problem?
Correct answer: Algebraic
Q18. Vu-Topper RM (1 marks)
Wilson’s model (Purchasing model with no shortages) is of the ___ type. A. Probabilistic
Related MTH601 files
All MTH601 files →- MTH601 Midterm Solved File 1 by Team Hadi Midterm PDF 1 MB
- MTH601 Midterm MCQs 2020 Midterm DOCX 827 KB
- MTH601 Midterm Questions by MM Midterm PDF 2.5 MB
- MTH601 Midterm Past Papers Mega File Midterm PDF 876 KB
- MTH601 Highlighted Handouts Set 2 by One Step to Success Highlighted PDF 8.2 MB
- MTH601 Grand Quiz Solution Quiz PDF 9.2 MB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.