Mth601 (Midterm Mcqs)
- Operations research (OR) is the application of quantitative methods to ___________ making.
Decision……confirm
- The first step in the application of ________ is to develop a network representation of the project plan.
CPM/PERT……confirm
- There are ___________ kinds of time calculations for a project.
4….confirm
Q4. In the phase of late start and late finish to find the critical path in a network flow diagram which of the following will be taken as latest finish time of the final event?
Early finish of final event
Q5. Which of the type of path will be critical in network flow diagram?
Longest path from starting node…….confirm
Q6. In a development project if an activity(m,n) of seven days duration, starts late on 3rd day then which of the following will be its latest finish time?
- While finding the Critical Path in the phase of Early start and Early finish computations, we start from first event and proceed calculations from left to right up to the _____ event.
Last…..confirm
- While finding the Critical Path in the phase of Late start and late finish we start from last node and the computations are performed from ___ up to the beginning event.
Bottom to up…..confirm
- The length of a path in a network is the total ________ it takes to travel along the path
Time…..confirm
- Choose the correct one for the project time that are used in project management.
Pert, CPM…..confirm
- In PERT, the possible variation in activity times is measured from Standard Deviation which is ________ of the difference between Pessimistic and Optimistic times.
One sixth……confirm
Q12. Which of the following is an operations research (OR) process?
Networking…..confirm
- In a network flow diagram, which of the following method through computations provides, start and completion times for each activity, critical and non critical activities and total and free slacks
CPM
- For a development project if its standard Normal variable = 1.38 expected and the scheduled durations of the project are 100 and 110 days respectively, then the standard deviation in the project length is
52.50
- In a network flow diagram, if two jobs a(I,j) and b(j,k) of durations 4 and 3 days duration finish late simultaneously on 7th day then on which of the following day the event I will finish earlier.
Related MTH601 files
All MTH601 files →- MTH601 Midterm Solved Paper 2005 Midterm PDF 279 KB
- MTH601 Midterm Mega File by Hussnain Ali Midterm PDF 24.2 MB
- MTH601 Midterm Notes Midterm PDF 10.7 MB
- MTH601 MCQs for Quizzes Midterm and Final Term Midterm PDF 21.6 MB
- MTH601 Highlighted Handouts by One Step to Success Highlighted PDF 8.1 MB
- MTH601 Grand Quiz Solution Quiz PDF 9.2 MB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.