- _______________ employs a different modeling and solution logic than linear programming
(a). Transportation Model (b). Inventory Control Model
(c). Dynamic Programming
- To identify and maintain the proper precedence relationship between activities those are not connected by event, we introduce
(a). Parallel Activity
(b). Dummy Activity
(c). Sequential Activity
- EST and EFT of activities are calculated in
(a). Forward pass
(b). Backward pass
- Critical path is obtained by connecting the jobs having
(a). Activities having same EST and LST (b). Activities having same EFT and LFT (c). Activities having zero slack
(d). All of the above
- The Variance Vt of expected time is calculated as
- In LP problems Additivity means that
(a). The effect of two different programs of production is the same as that of a joint program (b). The doubling (or tripling) the product will exactly double (or triple) the profit and the required resource (c). Both (a)& (b)
- Two of the first steps of OR process encompass the actual use of OR techniques. These steps are
(a). Model Construction and Model Solution
(b). Observation and Implementation (c). Definition of the problem and Model Solution (d). Model Solution and Implementation of results
- Let FS = Free Slack, TS = Total Slack, INDS = Independent Slack, then which relation is true
(a). TS ≤ FS (b). INDS ≤ FS (c). FS ≤ TS
(d). Both (b) & (c)
- Best possible time estimate that a given activity would take under normal conditions which often exist, is called
(a). Most Likely time estimate
(b). Pessimistic time estimate (c). Smallest time estimate
- Standard Deviation S.D is
(a). One sixth of the difference between pessimistic time estimates and optimistic time estimates (b). One sixth of the difference between pessimistic time estimates and most likely time estimates (c). One sixth of the difference between optimistic time estimates and most likely time estimates (d). One sixth of the difference between most likely time estimates and optimistic time estimates
Correct answer: Forward pass
Q2. _________________ may be less than most likely time estimate (1 marks)
Correct answer: Pessimistic time estimate
Q3. The dummy activities consume (1 marks)
Correct answer: No time, no resources
Q4. If an activity consumes no time and no resources then this activity is called __________. (1 marks)
Correct answer: dummy activity
Related MTH601 files
All MTH601 files →- MTH601 Midterm Solved MCQs Mega File 2 Midterm PDF 200 KB
- MTH601 Midterm Past Paper Spring 2005 Midterm PDF 306 KB
- MTH601 Midterm Past Paper 2023 by Ali Midterm PDF 4.5 MB
- MTH601 Midterm Past Paper Spring 2009 Midterm PDF 153 KB
- MTH601 Highlighted Handouts Highlighted PDF 7.4 MB
- MTH601 Quiz 2 Lectures 12-18 Quiz PDF 4.2 MB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.