Q1. of 10 ( Start time: 06:02:36 PM ) Total Marks: 1
Which of the following value is correct for the Variance of an activity times having optimistic, pessimistic and most likely values as 4, 8 and 6 days respectively?
- 147
- 666
0.444
Q2. of 10 ( Start time: 06:04:06 PM ) Total Marks: 1
The task which is executed by the usage of resources and time is called -------------.
node
event
project
activity
Q3. of 10 ( Start time: 06:05:37 PM ) Total Marks: 1
In a development project, if an activity (i,j) of six days duration, starts late on 3rd day then which of the following will be its latest finish time?
9th day 2nd day
3rd day
18th day
Q4. of 10 ( Start time: 06:07:06 PM ) Total Marks: 1
For any activity (i,j), if , a) Earliest start time of ‘i’ = Latest finish time of ‘i’, b) Earliest start time of ‘j’ = Latest finish time of ‘j’, c) difference of Earliest start times of events ‘i’ and ‘’j = difference of Latest finish times of events ‘i’and ‘j’ = time to complete the job, then the activity (i,j) is said to be -------.
dummy
critical
non-Critical non of the above
Q5. of 10 ( Start time: 06:08:32 PM ) Total Marks: 1
If both jobs ‘a(l,n)’ and ‘b(m,n)’ of ‘7’ and ‘8’ days durations respectively, start earlier simultaneously on 4th day, then ‘n’ can start earlier on -----------day.
8th
11th
15th
12th
Q6. of 10 ( Start time: 06:10:03 PM ) Total Marks: 1
In a network flow diagram, if an event is the predecessor of three other events then how many dummies are inevitable to include in the network?
One
Two
Four
Three
Q7. of 10 ( Start time: 06:10:57 PM ) Total Marks: 1
Which of the following times are not directly related to the activity cost as there is no certainty of time in such activities so their duration cannot be reduced, hence the cost cannot be expressed correctly?
CPM Times
PERT Times
Q8. of 10 ( Start time: 06:12:21 PM ) Total Marks: 1
Which of the following relation is true among the probabilistic times in PERT?
Most Likely < Optimistic < Pessimistic
Optimistic < Most Likely < Pessimistic
Most Likely < Pessimistic < Optimistic
Pessimistic < Most Likely < Optimistic
Q9. of 10 ( Start time: 06:13:49 PM ) Total Marks: 1
Which of the following technique to solve the net work flow diagrams, is activity oriented?
Programme Evaluation and Review Technique
Critical Path Method
Q10. of 10 ( Start time: 06:15:19 PM ) Total Marks: 1
In a network flow diagram, two jobs (i,j) and (i,k) of ‘9’and ‘6’ days duration leaves the node ‘i’ then which of the following will be Late start time for ‘i’, if it is provided that both (i,j) and (i,k) finish late on 12th and 8th day respectively?
6th day
2nd day 3rd day 1st day
Related MTH601 files
All MTH601 files →- MTH601 Official Handouts Official handout PDF 2.6 MB Free
- MTH601 Midterm Important Questions 2024 Midterm PDF 147 KB
- MTH601 Grand Quiz Solution 2020 by Sonu Ilyas Quiz PDF 3.8 MB
- MTH601 Quiz 1 Spring 2021 by Riz Mughal Quiz PDF 2 MB
- MTH601 Grand Quiz Solution Quiz PDF 9.2 MB
- MTH601 Quiz File Quiz PDF 21.6 MB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.