Skip to content
VUBuddy

MTH601 Quiz 1 Solution

Operations Research PDF 535 KBUpdated 23 Oct 2026
Quiz MTH601 Quiz 1 Solution PDF 535 KB
vubuddy.com
Type
Quiz
Course
MTH601 Operations Research
Size
PDF 535 KB
Updated
23 Oct 2026
Free download 0 of 3 used today
Download free · 535 KB

You get 3 free files a day on the website. Add the Chrome extension for 30 a day.

Unlimited downloads in the Android app Get it free on Google Play

Preview text

Text from pages 1, 2, 3 of 3. Download the file for all 3 pages.

Q1. of 10 ( Start time: 06:02:36 PM ) Total Marks: 1

Which of the following value is correct for the Variance of an activity times having optimistic, pessimistic and most likely values as 4, 8 and 6 days respectively?

  1. 147
  2. 666

0.444

Q2. of 10 ( Start time: 06:04:06 PM ) Total Marks: 1

The task which is executed by the usage of resources and time is called -------------.

node

event

project

activity

Q3. of 10 ( Start time: 06:05:37 PM ) Total Marks: 1

In a development project, if an activity (i,j) of six days duration, starts late on 3rd day then which of the following will be its latest finish time?

9th day 2nd day

3rd day

18th day

Q4. of 10 ( Start time: 06:07:06 PM ) Total Marks: 1

For any activity (i,j), if , a) Earliest start time of ‘i’ = Latest finish time of ‘i’, b) Earliest start time of ‘j’ = Latest finish time of ‘j’, c) difference of Earliest start times of events ‘i’ and ‘’j = difference of Latest finish times of events ‘i’and ‘j’ = time to complete the job, then the activity (i,j) is said to be -------.

dummy

critical

non-Critical non of the above

Q5. of 10 ( Start time: 06:08:32 PM ) Total Marks: 1

If both jobs ‘a(l,n)’ and ‘b(m,n)’ of ‘7’ and ‘8’ days durations respectively, start earlier simultaneously on 4th day, then ‘n’ can start earlier on -----------day.

8th

11th

15th

12th

Q6. of 10 ( Start time: 06:10:03 PM ) Total Marks: 1

In a network flow diagram, if an event is the predecessor of three other events then how many dummies are inevitable to include in the network?

One

Two

Four

Three

Q7. of 10 ( Start time: 06:10:57 PM ) Total Marks: 1

Which of the following times are not directly related to the activity cost as there is no certainty of time in such activities so their duration cannot be reduced, hence the cost cannot be expressed correctly?

CPM Times

PERT Times

Q8. of 10 ( Start time: 06:12:21 PM ) Total Marks: 1

Which of the following relation is true among the probabilistic times in PERT?

Most Likely < Optimistic < Pessimistic

Optimistic < Most Likely < Pessimistic

Most Likely < Pessimistic < Optimistic

Pessimistic < Most Likely < Optimistic

Q9. of 10 ( Start time: 06:13:49 PM ) Total Marks: 1

Which of the following technique to solve the net work flow diagrams, is activity oriented?

Programme Evaluation and Review Technique

Critical Path Method

Q10. of 10 ( Start time: 06:15:19 PM ) Total Marks: 1

In a network flow diagram, two jobs (i,j) and (i,k) of ‘9’and ‘6’ days duration leaves the node ‘i’ then which of the following will be Late start time for ‘i’, if it is provided that both (i,j) and (i,k) finish late on 12th and 8th day respectively?

6th day

2nd day 3rd day 1st day

All MTH601 files →
MTH601 Operations Research All MTH601 handouts, past papers, quizzes and MCQs in one place. Open course page

Get more out of VUBuddy, for free

Android app Free on Google Play
  • Unlimited downloads
  • The explanation behind every MCQ answer
  • Study offline on slow data
Get the Android app
Chrome extension Free on the Chrome Web Store
  • 30 downloads a day instead of 3
  • Sign in and buy Pro Semester here
Add to Chrome

One Pro Semester membership works in both the extension and the app.