Which of the following is an operations research (OR) process?
A. B. C. D. Implementation
Choose the correct one for the project times that are used in project management. A. Latest start time, Latest finish time, PERT, Earliest finish time B.
Latest start time, Latest finish time, Earliest start time, Earliest finish time
C. PERT, CPM D. Latest start time, Latest finish time, Earliest start time, CPM
A. B. C. D.
In a network flow diagram, for an activity (i,j) of duration of three days, if its earliest start time is of two days then which of the following will be its early finish time?
A. One and half day B.
Five days
C. Six days D. One day
Finish computations, we start from first event and proceed calculations from left to right up to the ---------- event. A. arbitrary B.
starting
C. middle D. list
In a development project, if an activity (q,r) of five days duration, starts late on 2nd day then which of the following will be its latest finish time?
A.
7th
B. 4th C. 10th D. 3rd
Operations research (OR) is the application of _________ methods to decision making. A. engineering B.
quantitative
C. computing D. all
If the variance of the project length = 25, expected and scheduled times are 40 and 36 respectively, then the Standard Normal Variable of the given project is-------------. A.
- 16
B.
.-0.80
C. -0.16 D.
- 80
A. B. C. D.
Which of the following relation is correct for the Standard Deviation of an activity times having optimistic, pessimistic and most likely values as 4, 8 and 6 days respectively? A.
- 111
B.
0.666
C.
- 1
D.
- 147
Which of the following is an operations research (OR) process? A. B. Solution C. D.
In a development project, if an activity (m,n) of seven days duration, starts late on 5rd day then which of the following will be its latest finish time?
A.
12th
B. 5th C. 7th D. 5th or 7th
Finish computations, we start from -------- event and proceed calculations from left to right up to the final event. A. arbitrary B. last C. middle D.
first
Which of the following is uncertain in PERT?
A. Activities’ precedence relation B. Resources associated with each activity C.
Related MTH601 files
All MTH601 files →- MTH601 Handouts by VUBuddy Handout PDF 5.6 MB
- MTH601 Midterm Past Papers Midterm PDF 4.6 MB
- MTH601 Quiz 3 Solution 2026 by Iqra Azhar Quiz PDF 833 KB
- MTH601 Grand Quiz Solution Spring 2021 by Riz Mughal Quiz PDF 998 KB
- MTH601 Subjective Subjective PDF 7 MB
- MTH601 Quiz Solution by Saima Kanwal Quiz DOCX 18 KB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.