CS615 Final Term Solved MCQs by Junaid
- Type
- Final term past paper
- Course
- CS615 Software Project Management
- Size
- PDF 731 KB
- Updated
- 23 Oct 2026
You get 3 free files a day on the website. Add the Chrome extensionSign in with the extension for 30 a day.
Preview text
Text from pages 2, 3, 4 of 14. Download the file for all 14 pages.
- When a project is being performed under contract, the product description is
- The buyer
The project sponsor
- The project manager
- The contractor
- Span of control in project management is the range of employees who to report to a
Managerial position
PG # 58
Developer
Customer
None of the given
- Resource allocation task is performed in phase
Project initiation
PG # 78
Project closedown
Project planning, control, and tracking
Product implementation
- Auditing is activity of
o Construction
o Design
o SCM
PG # 110 & 114
o Testing
- associated with constraints imposed by management or the marketplace.
Business impact-risks
PG # 318
Product size-risks
Process definition-risks
Customer characteristics-risks
- The training plan NOT contain the activity Training Courses Training Schedule
Software Components for Installation PG # 406
Roles and Responsibilities
- is an evolutionary life cycle model that combines the linear nature of the Waterfall model and the iterative nature of the Prototyping model The RAD Model The Waterfall Model The Prototyping Model
The Spiral Model
PG # 68
- People are managed through an organizational structure. This hierarchical structure is based on the cornerstones of management Three Four
PG # 193
Five
Two
- Traditional structures of business organization are of types
o 4
PG # 201
o 5
o 1
o 3
- Specify any company or industry-specific standards that are relevant to performing the work is called Deliverables Schedule
Applicable Standards
PG # 221
Acceptance Criteria
Special Requirements
- To calculate the estimated effort using the intermediate COCOMO technique, you use the formula: E = AEF *Ei E = FEA *Ei E = AFE *Ei
E = EAF *Ei
PG # 236
- Using the intermediate COCOMO technique effort is calculated in Five-step Process Two-step process
Three-step process
PG # 234
Four-step process
- WBS is not
A listing of tasks or activities
PG # 249
Should have at least 2 levels: Level 1 defines 100% of the service/product/result; Level 2 defines the deliverables in terms of work (groupings)
Project Management (and sub-contract management) at Level 2.
The deliverables in the WBS must match the scope or contract (WBS should not contain work that is not defined in the scope -Scope should not describe work not contained in the WBS)
- is NOT a guideline for creating a software project schedule. Classification Interdependence
Decomposition
PG # 288
Validation criteria
- Dividing a software project into phases helps you in managing the_____involved in the software project. Complexities Uncertainties
Complexities, Uncertainties
PG # 66
Size
- Unstructured and hurried software development is a Technology-related problem Product-related problem
Process-related problem
PG # 87
People-related problem
- We use when the organization is small, geographically centralized, and provides few goods and services.
Related CS615 files
All CS615 files →- CS615 Final Term Solved Quizzes Final term PDF 705 KB
- CS615 Final Term Past Paper 1 Final term PDF 60 KB
- CS615 Final Term Solved MCQs with References by Arslan Final term PDF 451 KB
- CS615 Final Term Solved Mega File Final term PDF 1.3 MB
- CS615 Highlighted Handouts Set 3 by VUBuddy Highlighted PDF 4.6 MB
- CS615 Quiz 3 by VU Topper RM Quiz PDF 227 KB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.