MTH601 FINAL TERM SOLVED MCQs FILE
(VISIT VURANK FOR MORE)
- _______________ employs a different modeling and solution logic than linear programming (a). Transportation Model
(b). Inventory Control Model
(c). Dynamic Programming
- To identify and maintain the proper precedence relationship between activities those are not connected by event, we introduce
(a). Parallel Activity
(b). Dummy Activity
(c). Sequential Activity
- EST and EFT of activities are calculated in
(a). Forward pass
(b). Backward pass
- Critical path is obtained by connecting the jobs having
(a). Activities having same EST and LST (b). Activities having same EFT and LFT (c). Activities having zero slack
(d). All of the above
- The Variance Vt of expected time is calculated as
- In LP problems Additivity means that
(a). The effect of two different programs of production is the same as that of a joint program (b). The doubling (or tripling) the product will exactly double (or triple) the profit and the required resource (c). Both (a)& (b)
- Two of the first steps of OR process encompass the actual use of OR techniques. These steps are
(a). Model Construction and Model Solution
(b). Observation and Implementation (c). Definition of the problem and Model Solution (d). Model Solution and Implementation of results
- Let FS = Free Slack, TS = Total Slack, INDS = Independent Slack, then which relation is true (a). TS ≤ FS
(b). INDS ≤ FS (c). FS ≤ TS
(d). Both (b) & (c)
- Best possible time estimate that a given activity would take under normal conditions which often exist, is called (a). Most Likely time estimate
(b). Pessimistic time estimate (c). Smallest time estimate (d). None of the above
- Standard Deviation S.D is
(a). One sixth of the difference between pessimistic time estimates and optimistic time estimates (b). One sixth of the difference between pessimistic time estimates and most likely time estimates (c). One sixth of the difference between optimistic time estimates and most likely time estimates (d). One sixth of the difference between most likely time estimates and optimistic time estimates The amount of an activity can be delayed without affecting the early start time of any other job, is called
Correct answer: Forward pass
Related MTH601 files
All MTH601 files →- MTH601 Final Term Past Paper Feb 2024 by VUBuddy Final term PDF 357 KB
- MTH601 Final Term Past Papers by MM Final term PDF 3.2 MB
- MTH601 Final Term Solved Paper Final term PDF 459 KB
- MTH601 Final Term MCQs by Waqas Qureshi Final term PDF 7.5 MB
- MTH601 Official Handouts Official handout PDF 2.6 MB Free
- MTH601 Practice Questions Lectures 5-6 Quiz PDF 35 KB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.