Skip to content
VUBuddy

MTH601 Midterm Past Paper 2006

Operations Research PDF 117 KBUpdated 23 Oct 2026
Midterm past paper MTH601 Midterm Past Paper 2006 PDF 117 KB
vubuddy.com
Type
Midterm past paper
Course
MTH601 Operations Research
Size
PDF 117 KB
Updated
23 Oct 2026
Free download 0 of 3 used today
Download free · 117 KB

You get 3 free files a day on the website. Add the Chrome extension for 30 a day.

Unlimited downloads in the Android app Get it free on Google Play

Preview text

Text from pages 1, 2 of 3. Download the file for all 3 pages.

MTH601 Midterm 2006 Paper - Operations Research

MTH601 Midterm Question Paper of Operations Research

fall 2006 - Session 6

Marks = M = 40 Time: 60min

Calculate the (i). EST, EFT, LST and LFT for each activity. (ii). Total Float, Free Float and Independent Float. (iii). Critical activities and Critical Path.

An Automobile factory manufacturers a particular type of gear within the factory. This gear is used in the final assembly. The particulars of this gear are: Demand rate =14000 units/year Manufacturing rate =35000 units/year Set up cost =Rs 500 per set up Holding cost = Rs 15/units/year Determine: (a) The optimum manufacturing quantity. ( (b) The maximum inventory. (c) The time between orders. (d) The number of orders/year. (e) The time of manufacture. (f) The optimum annual cost if the cost of the item per unit is Rs. 25

Consider the following problem, Solve graphically

Minimize. Z = 3X1 + 2X2 Subject to 2X1 + X2 ≥ 10 -3X1 + 2X2 ≤ 6 X1 + X2 ≥ 6 X1 , X2 ≥ 0

Which one is best describe Sectoral planning

  1. Inventory Planning in agriculture
  2. Improving the layout of a workshop in a company
  3. Simulation Modeling of the Economy of the country
  4. None of these.

_________________ is the most appropriate to situations where we maintain a relative stable employment levels and utilize the resource at a more constant rate

  1. (a). Resource Leveling Program
  2. (b). Resource Allocation Program
  3. (c). Both a & b
  4. (d). None of these.

If the slack time is zero, it means that the project will be

  1. Delayed
  2. Completed on schedule

The amount of an activity can be delayed without affecting the early start time of any other job, is called

All MTH601 files →
MTH601 Operations Research All MTH601 handouts, past papers, quizzes and MCQs in one place. Open course page

Get more out of VUBuddy, for free

Android app Free on Google Play
  • Unlimited downloads
  • The explanation behind every MCQ answer
  • Study offline on slow data
Get the Android app
Chrome extension Free on the Chrome Web Store
  • 30 downloads a day instead of 3
  • Sign in and buy Pro Semester here
Add to Chrome

One Pro Semester membership works in both the extension and the app.