MTH601 Midterm Solved MCQs Set 2 by Junaid

Operations Research PDF 1.5 MBUpdated 23 Oct 2026
Midterm past paper MTH601 Midterm Solved MCQs Set 2 by Junaid PDF 1.5 MB
vubuddy.com
Type
Midterm past paper
Course
MTH601 Operations Research
Size
PDF 1.5 MB
Updated
23 Oct 2026
Free download 0 of 3 used today
Download free · 1.5 MB

You get 3 free files a day on the website. Add the Chrome extension for 30 a day.

Unlimited downloads in the Android app Get it free on Google Play

Preview text

Text from pages 2, 3, 4 of 29. Download the file for all 29 pages.

1- Which of the following correspond to the practical limitation of available resource while modeling a real life situation into a linear program?

  •  Constraints
  •  Objective function
  •  Linear function
  •  Decision variables

2- Which of the following method follows iterative procedure to solve a linear programming problem?

  •  Graphical
  •  Algebraic(Simplex)

3Solution region of the constraints :2x+3y>12 and 2x+3y<12 will be the_____.

  •  Point(6,4)
  •  Straight line:2x+3y-12
  •  Empty set
  •  All first quadrant

4In the graph of the purchasing model with shortages the area under the horizontal axis represents________.

  •  Set up cost of item
  •  Purchase cost of item
  •  Carrying cost of item
  •  Shortage cost of item

5The straight line associated with the constraints 2x+3y<12 will meet xaxis at a distance of______ units from origin.

  •  2
  •  4
  •  6
  •  3

6Which of the following value is correct for the expected time of an activity having optimistic, pessimistic and most likely times as 4,8 and 6 days.

  •  666 days
  •  466 days
  •  6 days (not sure)
  •  933 days

7- In a network flow a diagram for an activity(I,j) of duration of three days if its earliest start time is of two days then which of the following will be its early finish time?

  •  One and half day
  •  One day
  •  Six days
  •  Five days (not sure)

8- In a development project. If an activity (m,n) of seven days duration starts late on 5rd day then which of the following will be its latest finish time?

  •  7th day
  •  5th or 7th day
  •  12th day
  •  5th day

9- Which of the following is an intermediate step to model a linear programming problem?

  •  Identify the objective function.
  •  Identify the non-negative restrictions and constraints
  •  Identify the unknown decision variables
  •  None of these

10A/An ________ is the collection of inter related activities to be performed in a particular sequence to completion.

  •  Project
  •  Branch
  •  Event
  •  Node

11- Which of the following times are directly to the activity cost that is by reducing the activity duration the direct cost of the corresponding activity is increased?

  •  PERT Times
  •  CPM Times

12- Which of the following is an operation research (OR) process?

  •  Linear programming
  •  Networking

13In the purchasing Model with shortages the cost function C(S,Q) can also be expressed as function of_______.

  •  (S,D)
  •  (Q,D)
  •  (S.t)
  •  (t,D)
All MTH601 files →
MTH601 Operations Research All MTH601 handouts, past papers, quizzes and MCQs in one place. Open course page

Get more out of VUBuddy, for free

Android app Free on Google Play
  • Unlimited downloads
  • The explanation behind every MCQ answer
  • Study offline on slow data
Get the Android app
Chrome extension Free on the Chrome Web Store
  • 30 downloads a day instead of 3
  • Sign in and buy Pro Semester here
Add to Chrome

One Pro Semester membership works in both the extension and the app.