Q1. Find the critical path and the expected duration of the following project.
Solution
There are 7 possible paths to get from the starting point at node 1 and travel through the network to end at node 8.
1-2-3-5-7-8=A-C-E-H-K=5+11+7+6+3=32
1-2-3-5-6-8=A-C-E-I-J=5+11+7+5+8=36 1-3-5-7-8=B-E-H-K=7+7+6+3=23
1-3-5-6-8=B-E-I-J=7+7+5+8=27 1-4-5-6-8=D-F-I-J=3+9+5+8=25
1-4-5-7-8=D-F-H-K=3+9+6+3=21 1-4-6-8=D-G-J=3+12+8=23
Hence the critical path is the longest distance with the shortest possible time i.e. =1-2-3-5-6-8
=A-C-E-I-J =5+11+7+5+8
=36 I(5) A(5) C(11)
D(3) B(7) E(7) H(6)
K(3)
G(12) J(8) LST=LFTDuration of the activity
- 1-2-5-8-9=2+4+1+3=10
- 1-3-7-8-9-=2+5+4+3=14
- 1-3-6-9=2+8+5=15
- 1-4-6-9=1+3+5=9
Hence 1-3-6-9 is the critical path with duration 15.
Q4. A small marketing project consists of the jobs as shown in the table below.
Activity
X Y Z X
a) Draw the Network diagram. b) Calculate the following time estimates.
- Earliest Start Time of each activity
- Earliest Finish Time of each activity
- Latest Start Time of each activity
Latest Finish Time of each activity
Solution
a) Network:
Z(6) X(4)
Y(5)
Related MTH601 files
All MTH601 files →- MTH601 Official Handouts Official handout PDF 2.6 MB Free
- MTH601 Midterm Quiz 1 Midterm PDF 10.8 MB
- MTH601 Solution Lectures 11-12 Updated Quiz PDF 29 KB
- MTH601 Grand Quiz Solution Quiz PDF 9.2 MB
- MTH601 Quiz Solution by Aziz Raaj Quiz PDF 106 KB
- MTH601 Grand Quiz Solution 2020 by Sonu Ilyas Quiz PDF 3.8 MB
Get more out of VUBuddy, for free
- Unlimited downloads
- The explanation behind every MCQ answer
- Study offline on slow data
- 30 downloads a day instead of 3
- Sign in and buy Pro Semester here
One Pro Semester membership works in both the extension and the app.